Off The Cloud H10 Private AI Pod · Rev 1.0

Product description & installation planning guide

GPU-ready infrastructure for private, always-on AI at home or on site: a main pod plus an outdoor utility skid.

01Product overview

H10 gives a household or private workspace a dedicated place to run AI workloads and keep selected data and services under the owner's control. It combines GPU-ready space, power, cooling, backup, monitoring and secure network boundaries in one supportable installation. Compute is serviced inside the pod; heat rejection, battery and power equipment sit on a separate utility skid with its own service space.

CapabilityWhat H10 providesYour benefit
Private compute boundaryDedicated racks, isolated networks, local storage interfaces, optional offline operationSensitive workloads stay under your access policies
GPU-ready plantRack positions, protected power, cooling interfaces, monitoring, safe shutdownChoose compatible compute without redesigning the room
Residential deploymentAcoustic, weather, service-clearance, safety and remote-monitoring needs handled as one systemA supportable installation instead of an improvised server stack
Expandable platformStandard and Pro capacity with modular utility equipmentCapacity matched to your site and workload

Package boundary

Included

Main pod enclosure; two 19-inch rack positions; internal trays and labeled interfaces; utility skid with UPS and battery, CDU and heat-rejection equipment; protection and distribution; environmental and leak sensors; local alarms; controller and monitoring; factory integration and acceptance test.

Supplied separately

GPU servers (available as configurator options); application and model licenses; storage beyond the agreed base; site foundation and utility feeder; permits; your network and internet service; crane and delivery unless quoted; optional generator or second cooling train.

02Configurations

Design itemH10 StandardH10 Pro
IT design load10 kW continuous20 kW continuous
RacksOne compute rack + one storage, network and expansion rackTwo compute-capable racks
Total running load (IT + cooling and auxiliaries)12–13.5 kW24–27 kW
Running current, 208 V 3-phase≈35–39 A≈70–79 A
Running current, 480 V 3-phase≈15–17 A≈30–34 A
Outdoor heat rejection, starting point≈12 kW≈24 kW
UPS target10–15 min for agreed critical loads10–15 min for agreed critical loads
Night noise objective≤45 dBA at agreed receptorSame; larger outdoor equipment may need added acoustic treatment

External envelope 2991 × 2438 × 2591 mm. Preliminary interior clear envelope 2791 × 2238 mm. Racks are approximately 800 mm wide × 1000 mm deep, 24–32U class. Currents assume power factor 0.95. 10 kW and 20 kW refer to IT load only; the site connection must also cover cooling, pumps, UPS losses, battery recharge, controls and lighting.

03Space planning & service clearances

RACK A 800 × 1000 RACK B 800 × 1000 FRONT SERVICE 900 mm REAR 600 mm END · 291 mm SIDE CHASE ≈638 mm, not an equipment bay interior length 2791 mm width 2238 mm
ZoneTargetPurpose
Front service aisle900 mmDoor swing, operator access, rail extension and server replacement
Rack band1000 mmTwo 800 × 1000 mm racks side by side, including rear connectors and liquid couplings
Rear service area600 mmCable and coolant access, airflow return, inspection and leak checks
End allowance≈291 mmTaken by door frame, end manifold and seals; not usable for equipment
Side chase≈638 mmNarrow chase only; does not house UPS, batteries or CDU

Before fabrication we obtain dimensioned drawings for the exact racks, servers, CDU interface and door, then mark out a 1:1 floor mock-up to prove door access, server extraction and the replacement route.

04System architecture

ModuleLocationRole
Main podOutdoor foundation or hardstandWeather-resistant enclosure, two rack positions, service aisles, cable trays, sensors, access control, local alarm, labeled penetrations
Compute racksInside the podGPU servers installed after interface approval, on separate power branches with identified network and coolant connections
Utility skidOutside, next to the podUPS and battery, main isolation and metering, CDU, pumps, filters, expansion and air removal, controller
Heat-rejection unitOutdoor, away from openingsDry cooler sized for the site's design ambient, placed to avoid recirculation and noise
Residential interfaceBetween site, pod and skidElectrical feeder, bonding, network, alarm contacts, emergency stop, coolant piping, sealed penetrations

05Electrical system & UPS

Site feeder→Main isolation & overcurrent→Metering & surge protection→UPS + maintenance bypass→PDU A/B→Your GPU servers
ParameterStandardPro
Cooling and auxiliaries20–35% of IT20–35% of IT
Breaker to plan for, 208 V 3-phase50 A100 A
Breaker to plan for, 480 V 3-phase25 A45 A
Usable UPS energy, 15 min at full IT2.5 kWh5.0 kWh
Battery nameplate, initial sizing≈3.3 kWh≈6.6 kWh

Breaker sizes apply the 125% continuous-load rule to the upper running current and round up to a standard size. They are planning values, not an approved design; a licensed electrician sizes and coordinates the feeder, protection and earthing for your jurisdiction.

On utility loss, the UPS carries the agreed critical loads. The controller notifies the workload manager, checkpoints or stops jobs where possible, limits server power and starts an orderly shutdown, keeping pumps running until servers reach a safe temperature. Generator operation is optional and requires transfer and compatibility testing.

06Liquid cooling & heat rejection

GPU cold plates→Facility CDU→Filter & expansion→Dry cooler
Thermal design pointStandardPro
IT heat to reject10 kW20 kW
Outdoor heat rejection (incl. 20% margin)≈12 kW · 40,900 BTU/h≈24 kW · 81,900 BTU/h
Residual air cooling2–3 kW4–6 kW

The system monitors supply and return temperature, flow, differential pressure, rack inlet temperature, CDU status and leak sensors. Low flow, high supply temperature, pump failure or a leak triggers staged power limiting and a controlled shutdown, not just an alarm. Dual loop means the IT and facility liquid circuits are separated; N+1 redundancy is a separate option.

07Network, data protection & local control

ZoneTypical systemsDefault policy
WAN / remote accessInternet link, firewall, VPN or zero-trust gatewayNo inbound exposure. MFA, named accounts, time-limited support, audit logs
ManagementServer BMC, UPS and CDU controllers, environmental monitoringDedicated subnet with restricted devices and roles
AI / storageGPU servers, model store, NAS, backup target, local APIsSeparate from user and IoT networks; stored data encrypted with keys you own
Home / IoTCameras, locks, sensors, automation, household devicesIsolated from management; only the integrations you need

Offline mode. Without internet, local inference, knowledge search, storage and home automation continue. Model, firmware and container updates use signed packages in an approved maintenance window.

Backups. At least one backup lives outside the pod, because disks in the same enclosure don't protect against fire, theft or site damage. Restores are tested on a schedule.

08Site, structure, safety & environment

DisciplineWhat we assessEvidence at acceptance
Foundation & structureSoil bearing, weights, wind, seismic, flood, anchors, lifting points, drainageSigned calculations; anchor and bonding inspection
Weather & waterRoof slope, seals, penetrations, condensation, leak collectionWater-ingress check; leak-sensor simulation
Fire & batteryBattery chemistry and capacity, thermal detection, shutdown logic, responder accessLocal fire review; alarm and isolation tests
Noise & vibrationFans, pumps, server airflow, barriers, night mode, bedroom and property-line distancesDay and night sound measurements
Access & replacementDoor width, server extraction, battery change path, lifting equipmentBring in and remove the largest component

Residential checklist: service capacity, distance to bedrooms and neighbors, setbacks, noise ordinances, delivery and crane access, airflow, drainage, grounding, electrical and fire requirements, network route and maintenance path. A home installation may need permits even though the pod is prefabricated.

09Installation, commissioning & acceptance

StageWorkPass condition
A · Site surveyUtility service, grounding, network, foundation location, sun and wind, noise receptors, delivery routeWritten service-capacity confirmation; permit path identified
B · Equipment freezeRack and server drawings, power profile, cooling ratio, UPS, CDU, dry-cooler and sound data1:1 layout passes; heat, flow and load schedules close
C · Factory integrationAssembly, pipe flush and pressure test, earthing, controls, leak and power-failure simulationsComplete factory acceptance test record
D · Site installationAnchoring, feeder, cooling lines, heat rejection, network, alarms, sealingPhotos, test records and as-built drawings agree
E · Performance testLoad steps 25/50/75/100%, sustained run, noise, UPS discharge, graceful shutdownNo unplanned thermal excursion, leak or alarm
F · HandoverAdministrator training, spare parts, credentials, restore drill, warranty, supportYou can shut down safely, restore data and reach service

10Operations, maintenance & service

IntervalChecks
Daily, automatedAlarms, rack inlet and coolant temperature, power, UPS state, pump and heat-rejection status, failed AI jobs
MonthlyFilters and airflow, coolant pressure, seals, door hardware, alarm history, backup freshness
QuarterlyData restore test, firmware review, UPS self-test, shutdown drill, remote-access audit
AnnuallyCoolant quality, bonding, thermal imaging, sound, fire interlocks, anchors, weather seals
ConditionAutomatic response
Utility power lostUPS carries critical loads; jobs checkpoint or stop; cooling runs through thermal rundown
Cooling fault or high temperatureAlarm, reduce GPU power, stop new jobs, controlled shutdown at the validated threshold
Leak or fireIsolate the affected zone, notify occupants and responders, follow the site emergency plan
Internet unavailableLocal services keep running; external support paths close; updates wait

11Product status

This manual is a preliminary product definition based on the H10 Rev 3 engineering concept. It supports product discussion, supplier quotes and site feasibility review. It is not a construction drawing, permit set, final bill of materials, guaranteed performance schedule or approved electrical or fire design. Final output, GPU count, sound level and availability depend on the servers you select and your verified site.